Tuesday, 26 October 2010

The "Situation Room" secure

Hi All. I last left the Situation room with a roof on. Since then things have progressed. The job that was done next was to render the outside. This is a two part process. Initially, a coarse render is applied that is up to a 1/2" thick. The reason for doing this was to create the "proper" water seal for the building. Noel commented on what appeared to be a lot of problems for a prefabricated building. I agree in the sense that I'm trying to take something for one purpose and make it fit for another. As a garage, it would be fine (but would need a very big car!) but once its insulated (unlike the original) then it must be water tight. The next piccy shows the first layer of coarse render.
This took a day to put on. Fortunately, September has been good weather and it was sufficiently dry to allow the fine render to go on the next day. This is similar in thickness. However, it takes two guys a day to do it. I never knew that render, or concrete for that matter, was polished. But it is. And the above render is done with graded trowels ending up with a steel one. The finished rendered building is below. At the same time I've included the progress on the flags for around the building and the new path. The Situation room was looking good. 
So there you have it, a nice looking building. This left two jobs to do. Painting it was an obvious choice and thankfully the weather was still on our side. Anne helped me paint the building and it took two and a half days. I always use a masonry paint, always Sandtex. Two coats were applied and we were fortunate because it did rain shortly after finishing the painting on the second day but the paint managed to cling on OK.
The last job was to redo the ridge line. As I said in earlier posts, the ridge line was essentially a tin cover, the cover being about 3mm thick and then the gaps in the eaves filled with a foam. The final part was to replace this with a proper ridge tile made of the same material as the roof panels and have it bedded in. The gable ends were also lead flashed, primarily to guard against capillary action of water moving inside in time of snow.
So here is the finished article (fingers crossed!).

I now need to get a new camera lens for taking piccies of the troops which have started to fill the ranks!

2 comments:

  1. Looks good Gerry. Looking forward to seeing the table and then some figs!
    Please also post when the WWII rules are actually released.
    Best of luck.
    Cheers,
    Chris

    ReplyDelete